Timeline

June (Concept)

Preliminary discussions with various ward members
Create general plan
Approval from the High Priest Group
Approval from the Bishopric
Ward Temple Day set
Ward Goal set


July (Planning)

Contact Temple for dates that are available
Set up procedure for managing names
  • Family Ordinance requests
  • Family Ordinance cards
  • Names that the family handles directly
Complete timeline
Develop tasks for the committees
  • Research
    • Develop process for individual committee members to follow for doing research
    • Assign lines to individual committee members for Lund Family or others that need assistance
    • Provide assistance to committee members as they do research
    • Report to whole group each Sunday on progress
    • Offer Services to entire Ward
  • Temple Ready
    • Develop process for individual committee members to follow for getting names Temple Ready
    • Assign names to individual committee members that need to be Temple Ready
    • Provide assistance to committee members as they get names Temple Ready
    • Report to whole group each Sunday on progress
    • Offer Services to the entire Ward 
Talks in Sacrament Meeting

August (Initial Roll Out and Fine Tuning)

Report progress to Ward Council & request assistance where needed
Roll out to the Ward Members (need someone to do this)
  • Ward Bulletin
  • Ward Web Site
  • Posters for Lobby
  • Update status of project
  • Email List of participants

September (Research and Temple Ready)

Report progress to Ward Council & request assistance were needed
Baptism Trip – Friday, September 3, 7:30 am,  Six endowed brethren and two endowed sisters to help proxies.  Ask YM/YW organizations to assist.  Goal 200 names
Initiatory Trips – TBD, we need to do all 200 baptisms to have them ready for October 23

October (Research and Temple Ready)

Report progress to Ward Council & request assistance were needed
Initiatory Trips – TBD
Ward Temple Trip – October 23
  • Baptisms, goal 500
  • Initiatorys, goal 50
  • Endowments, goal 150
  • Sealings, goal 300
November (Cleanup and Finalizing) 
Contact each family that participated and offer assistance with the remainder of their goal.
Complete a report and give to the Ward Council.